Project Items
Line | Item Number | Description | Units | Quantity |
---|---|---|---|---|
01-ROADWAY | ||||
1 | Special 11 | BLACK-MAT | SY | 20,121 |
2 | 614E11001 | MAINTENANCE OF TRAFFIC, AS PER PLAN | EA | 6 |
5 | 614E11000 | MAINTAINING TRAFFIC | LS | 1 |
02-INCIDENTALS | ||||
3 | 802E00001 | PREMIUM ON INDUSTRIAL INSURANCE | LS | 1 |
4 | 802E00002 | PREMIUM ON BID BOND | LS | 1 |
6 | 802E00003 | CONTINGENCIES THE CONTRACTOR SHALL ENTER $1.00 IN THE UNIT PRICE COLUMN AND $4753.00 IN THE TOTAL COLUMN. IF THE CONTRACTOR NEGLECTS TO ENTER THE CORRECT FIGURE(S), THE CONTRACTOR'S BID SHALL BE CORRECTED AND THE PROCESS FOR MISTAKE IN BID SHALL FOLLOW. THIS ITEM WILL BE USED IN THE EVENT THAT THERE ARE CHANGE ORDERS DURING THE CONTRACT. NO EXTRA WORK OR CHANGE ORDER WILL BE PAID OR RECOGNIZED UNLESS AGREED UPON IN WRITING BY AN AUTHORIZED REPRESENTATIVE OF THE BUTLER COUNTY ENGINEER. ANY ITEM OVER THE PLAN QUANTITY WILL NOT BE PAID UNLESS IT HAS BEEN APPROVED BY AN AUTHORIZED REPRENTATIVE OF THE BUTLER COUNTY ENGINEER'S OFFICE. |
EA | 4,753 |