Project Items
Line | Item Number | Description | Units | Quantity |
---|---|---|---|---|
01-ROADWAY | ||||
1 | 253E01000 | PAVEMENT REPAIR 8.5" |
SY | 101 |
2 | 614E11001 | MAINTENANCE OF TRAFFIC, AS PER PLAN | EA | 24 |
3 | 614E990002 | WORK ZONE SIGNS | EA | 8 |
4 | 614E21500 | WORK ZONE CENTER LINE, CLASS II, 642 PAINT | MILE | 1.15 |
5 | 642E00290 | CENTER LINE | MILE | 1.907 |
6 | 642E00090 | EDGE LINE, 4" | MILE | 3.814 |
7 | Special 11 | BLACK-MAT | SY | 80,226 |
8 | 614E11000 | MAINTAINING TRAFFIC | LS | 1 |
02-INCIDENTALS | ||||
9 | 802E00001 | PREMIUM ON INDUSTRIAL INSURANCE | LS | 1 |
10 | 802E00002 | PREMIUM ON BID BOND | LS | 1 |
11 | 802E00003 | CONTINGENCIES The Contractor shall enter $1.00 in the unit price column and $19,602.00 in the total column. If the Contractor neglects to enter the correct figure(s), the Contractor's bid will be corrected and the process for "Mistake in Bid" shall follow. This item will be used in the event that there are change orders in the Contract. No work will be paid or recognized under this item unless agreed upon in writing by an authorized representative of the Butler County Engineer's Office. |
EA | 19,602 |