Project Items
Line | Item Number | Description (Hide All Extended Descriptions) | Units | Quantity |
---|---|---|---|---|
DRAINAGE | ||||
601E32200 | ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | CY | 7.2 | |
602E20000 | CONCRETE MASONRY | CY | 10 | |
605E14000 | 6" BASE PIPE UNDERDRAINS | FT | 2,996 | |
611E01500 | 6" CONDUIT, TYPE F | FT | 150 | |
611E04400 | 12" CONDUIT, TYPE B | FT | 42 | |
611E04600 | 12" CONDUIT, TYPE C | FT | 324 | |
611E05900 | 15" CONDUIT, TYPE B | FT | 238 | |
611E06100 | 15" CONDUIT, TYPE C | FT | 32 | |
611E07400 | 18" CONDUIT, TYPE B | FT | 389 | |
611E07600 | 18" CONDUIT, TYPE C | FT | 329 | |
611E52700 | 29" X 45" CONDUIT, TYPE A, 706.04 | FT | 85 | |
611E98150 | CATCH BASIN, NO. 3 | EACH | 5 | |
611E98151 | CATCH BASIN, NO. 3, AS PER PLAN (Show Less) Modified |
EACH | 1 | |
611E98180 | CATCH BASIN, NO. 3A | EACH | 3 | |
611E98181 | CATCH BASIN, NO. 3A, AS PER PLAN (Show Less) Modified |
EACH | 3 | |
611E98370 | CATCH BASIN, NO. 6 | EACH | 1 | |
611E98470 | CATCH BASIN, NO. 2-2B | EACH | 2 | |
611E99574 | MANHOLE, NO. 3 | EACH | 2 | |
EROSION CONTROL | ||||
659E00300 | TOPSOIL (Show Less) 4" Depth |
CY | 460 | |
659E10001 | SEEDING AND MULCHING, AS PER PLAN | SY | 4,300 | |
659E35000 | WATER | MGAL | 22 | |
832E15000 | STORM WATER POLLUTION PREVENTION PLAN (Show Less) This item includes all costs associated with the development, implementation, inspection and the required documentation of a Storm Water Pollution Prevention Plan for the Project described in this Contract. all of the specifications and requirements of ODOT supplemental specification 832 shall apply. |
LS | 1 | |
832E30000 | EROSION CONTROL (Show Less) This item is for the installation of Storm Water BMPS as defined in appendix "F" of ODOT supplemental specifications 832. The Contractor shall enter $1.00 in the unit price column and $24,500.00 in the total column. If the Contractor neglects to enter the correct figure(s) the Contractors bid will be corrected and the process for "Mistake In Bid" shall follow. No work will be recognized or paid under this item unless agreed upon and approved by an authorized representative of the Butler County Engineer's Office. |
EACH | 24,500 | |
895E10030 | MANUFACTURED WATER QUALITY STRUCTURE, TYPE 3 | EACH | 1 | |
INCIDENTALS | ||||
614E11000 | MAINTAINING TRAFFIC | LS | 1 | |
623E10000 | CONSTRUCTION LAYOUT STAKES AND SURVEYING | LS | 1 | |
624E10000 | MOBILIZATION | LS | 1 | |
802E00001 | PREMIUM ON INDUSTRIAL INSURANCE | LS | 1 | |
802E00002 | PREMIUM ON BID BOND | LS | 1 | |
802E00003 | CONTINGENCIES (Show Less) The Contractor shall enter $1.00 in the unit price column and $65,000.00 in the total column. If the Contractor neglects to enter the correct figure(s), the Contractor's bid will be corrected and the process for "Mistake in Bid" shall follow. This item will be used in the event that there are change orders in the Contract. No work will be paid or recognized under this item unless agreed upon in writing by an authorized representative of the Butler County Engineer's Office. |
EA | 65,000 | |
PAVEMENT | ||||
301E46000 | ASPHALT CONCRETE BASE, PG64-22 | CY | 1,580 | |
304E20000 | AGGREGATE BASE | CY | 1,750 | |
407E20000 | NON-TRACKING TACK COAT | GAL | 1,100 | |
441E50000 | ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG64-22 | CY | 467 | |
441E50300 | ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2, (448) | CY | 470 | |
608E10000 | 4" CONCRETE WALK | SF | 8,950 | |
608E52000 | CURB RAMP | SF | 841 | |
609E12000 | COMBINATION CURB AND GUTTER, TYPE 2 | FT | 2,736 | |
609E26000 | CURB, TYPE 6 | FT | 1,016 | |
ROADWAY | ||||
201E11000 | CLEARING AND GRUBBING | LS | 1 | |
202E23010 | PAVEMENT REMOVED, ASPHALT | SY | 4,800 | |
202E32000 | CURB REMOVED | FT | 301 | |
202E32500 | CURB AND GUTTER REMOVED | FT | 34 | |
202E35100 | PIPE REMOVED, 24" AND UNDER | FT | 105 | |
202E35200 | PIPE REMOVED, OVER 24 | FT | 32 | |
202E58100 | CATCH BASIN REMOVED | EACH | 1 | |
203E10000 | EXCAVATION | CY | 1,530 | |
203E20000 | EMBANKMENT | CY | 1,720 | |
204E10000 | SUBGRADE COMPACTION | SY | 10,250 | |
204E13001 | EXCAVATION OF SUBGRADE, AS PER PLAN (Show Less) Subgrade Stabilization Contingency |
CY | 4,815 | |
204E21001 | GRANULAR EMBANKMENT, AS PER PLAN (Show Less) Subgrade Stabilization Contingency |
CY | 4,815 | |
204E45000 | PROOF ROLLING | HOUR | 4 | |
204E51001 | GEOGRID, AS PER PLAN (Show Less) Subgrade Stabilization Contingency |
SY | 9,760 | |
252E01500 | FULL DEPTH PAVEMENT SAWING | FT | 177 | |
253E01000A | PAVEMENT REPAIR (Show Less) 6 inch (Contingency) |
SY | 450 | |
254E01000 | PAVEMENT PLANING, ASPHALT CONCRETE | SY | 1,832 | |
616E10000 | WATER | MGAL | 50 | |
623E40501 | REFERENCE MONUMENT, AS PER PLAN | EACH | 4 | |
SANITARY SEWER | ||||
611E99654 | MANHOLE ADJUSTED TO GRADE | EACH | 1 | |
TRAFFIC CONTROL | ||||
621E00100 | RPM | EACH | 75 | |
630E03100 | GROUND MOUNTED SUPPORT, NO. 3 POST | FT | 67 | |
630E80100 | SIGN, FLAT SHEET | SF | 27 | |
630E84900 | REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | EACH | 7 | |
630E85100 | REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | EACH | 1 | |
630E86002 | REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSAL | EACH | 10 | |
644E00100 | EDGE LINE, 4 | MILE | 0.77 | |
644E00300 | CENTER LINE | MILE | 0.86 | |
644E00400 | CHANNELIZING LINE, 8 | FT | 402 | |
644E00500 | STOP LINE | FT | 25 | |
644E00600 | CROSSWALK LINE | FT | 85 | |
644E00900 | ISLAND MARKING | SF | 128 | |
644E01300 | LANE ARROW | EACH | 16 | |
644E30000 | REMOVAL OF PAVEMENT MARKING | FT | 780 | |
WATER WORK | ||||
638E09711 | 12" X 8" TAPPING SLEEVE, VALVE AND VALVE BOX, AS PER PLAN | EACH | 1 | |
638E10300 | FIRE HYDRANT EXTENDED AND ADJUSTED TO GRADE | EACH | 3 | |
638E10800 | VALVE BOX ADJUSTED TO GRADE | EACH | 4 | |
638E20092 | SPECIAL - 8" WATER MAIN DIP CLASS 53 BOLTLESS RESTRAINED JOINTS AND FITTINGS | FT | 45 | |
638E98000 | WATER WORK, MISC.: (Show Less) Water Purity Station Relocation |
EACH | 1 | |
638E98000 | WATER WORK, MISC.: (Show Less) 8" Water Main Stop (Cap) |
EACH | 1 |